Home >  Term: budgeted cost of work scheduled
budgeted cost of work scheduled

The earned value field that shows how much of the budget should have been spent, in view of the baseline cost of the task, assignment, or resource. BCWS is calculated as the cumulative timephased baseline costs up to the status date or today's date.

0 0

Kūrėjas

  • Romain
  •  (V.I.P) 17515 points
  • 44.44% positive feedback
© 2024 CSOFT International, Ltd.